The Public Works Department's Pavement Management Program (PMP) assigns a Pavement Condition Index ("PCI") to all city streets from 0-100, with 100 representing a surface condition similar to new pavement. Using the PMP, staff have identified specific street sections in the southwest residential quadrant, as well as 118th St. west of Aviation Blvd., as having PCI scores below 75. These streets are shown in the map below and will be addressed during the annual Pavement Rehabilitation Project.
Rehabilitation will be a two-inch grind and overlay for the most damaged street sections, while the remaining will be slurry sealed. Slurry sealing applies an asphalt emulsion onto existing pavement to prevent water intrusion.
Click here to see the project Notice of Construction.
On 1/9/26 the following sections were added to the project:
- Overlay: Virginia St. from Grand Ave. to El Segundo Blvd.
- Overlay: Loma Vista St. from Grand Ave. to El Segundo Blvd.
- Overlay: The south half of Loma Vista St. between Holly Ave. and Grand Ave.
- Slurry seal: Loma Vista St. from Holly Ave. to Grand Ave.